The Ontario Land Tribunal (OLT) has rendered its decision on Katasa’s appeal to permit the use of mechanical space on the 17th floor to become a […]
275 Carling Ave: Katasa Appeal
In January we learned of a minor variance request from Katasa for 275 Carling, to permit the use of mechanical space on the 17th floor to […]
Excavation for 275 Carling
The excavation process is finally about to wrap up. The last day of blasting is expected to be on Monday, April 4th. There may be a […]
All Shook Up – Blasting at ‘The Clemow’
By Sue Stefko(Appeared in the Glebe Report, December 2021) On the morning of November 2nd, a strong blast shook homes near the building site of The […]
Blasting Concerns Related to 275 Carling (‘The Clemow’)
There have been numerous complaints arising from the blasting occurring as part of the construction of 275 Carling. Blasting started in September, and so far, Katasa […]
275 Carling – Blasting to commence
The other Katasa development in our neighbourhood, the 16-storey retirement residence at 275 Carling, is already underway. The build will take approximately 2 and a half […]
275 Carling: The Next ‘Big Thing’ in the Glebe Annex
By Sue Stefko (Appeared in the Glebe Report, March 2021) Nearly a decade after a project was first proposed for 275 Carling Ave, construction is expected […]
Katasa’s retirement residence at 275 Carling receives site plan approval
The site plan was approved on November 19th. A description of the project can be found within the City of Ottawa’s approval documentation: “The construction of […]
275 Carling Ave – Katasa Retirement Residence
After many years in the works, including a change in ownership of the site, Katasa’s 16-storey retirement residence is nearing site plan approval. While we still […]
Retirement Residence at 275 Carling Avenue
There has been more activity on the site of 275 Carling Ave, Katasa’s proposed 16-storey retirement residence, since our last update. The site plan has not […]
Development Update: 289 Carling Ave & 275 Carling Ave
There have been some new fences going up in our neighbourhood lately, which have raised some questions about the status of those projects: 289 Carling Ave […]
Glebe Annex development update
Much development continues in and around the Glebe Annex: 275 Carling Ave – Taggart’s proposed retirement home at 275 Carling Ave is still in the site […]