By Sue Stefko (Appeared in the Glebe Report, October 2022) The six-storey, 40-unit John Howard Society (JHS) supportive-housing complex will soon welcome its first staff, residents […]
289 Carling – John Howard Society Questions and Answers
The John Howard Society has updated the ‘Questions and Answers’ document which helps provide answers to the most frequently asked questions they have received from residents […]
289 Carling – Bell S. re-opens
The John Howard Society has brought all the modules on site and Bell S has re-opened at Carling for vehicles and pedestrians. The building is tentatively […]
Closure of Bell St. South at Carling Starting 28 February
The John Howard Society has advised us that Bell St. S. will be closed at Carling from this Monday, February 28th to approximately March 9th, as […]
John Howard Society Names Residential Coordinator for the 289 Carling site
By Sue Stefko (Appeared in the Glebe Report, April 2021) With the construction of the John Howard Society (JHS) supportive housing development now into its fourth […]
Construction Continues at 289 Carling Ave
As much of the neighbourhood can hear – and feel – work continues at the John Howard Society site. The project has been designated “essential”, so […]
289 Carling Ave – John Howard Society Supportive Housing
The John Howard Society (JHS) 6-storey, 40-unit supportive housing residence received site plan approval on September 2nd. So far, the JHS has received a permit to […]
Next Steps for the Supportive Housing Site at 289 Carling Avenue
289 Carling Avenue is fenced off prior to the start of construction of the John Howard Society’s supportive housing for the chronically homeless. PHOTO: Gabrielle Dallaporta […]
John Howard Society Receives Site Plan Approval for 289 Carling Ave
The site plan application for the John Howard Society’s (JHS) planned 6-storey, 40 unit supportive housing project for the chronically homeless was approved on Wednesday, June […]
Development Update: 289 Carling Ave & 275 Carling Ave
There have been some new fences going up in our neighbourhood lately, which have raised some questions about the status of those projects: 289 Carling Ave […]
John Howard Society’s new building – plans progress
By Sue Stefko (Appeared in the Glebe Report, October 2019) The initial goal of starting construction in fall 2019 will not be met, but there has […]
289 Carling Site Plan
The John Howard Society (JHS) has released a site plan proposal for 289 Carling. There are no major surprises. As promised, the plan conforms to zoning, […]